Construction Updates

Printed Fri Jul 10 2020 18:30:31 GMT+0000 (Greenwich Mean Time)

Sunshine Hotel
Sihanoukville, Cambodia

  • Rebar installation for retaining wall.
  • Formwork installation for fresh water tank.
  • Casting concrete for fresh water tank.
  • Installed site safety net for elevator opening.
  • Rebar installation for pit of slab elevator.
  • Brick wall installation 1st floor.
  • Window frame installation 2nd floor.
  • Stairs plastered several floors.
  • Frame aluminum installation for bathroom 4th floor.
  • Floor and wall tile installation several floors.
  • Steel handrail installation several floors.
NaN/9

Bali Water World A
Bali, Indonesia

     1. Structural Works
          - Building A : 98%
          - Lower Ground Floor & Pool  : 43%
     2. Architectural Works
          - Building A  : 36%
     3. Mechanical, Electrical and Plumbing works (MEP)
          - Building A  : 34%

NaN/6

Bali Water World B
Bali, Indonesia

1. Structural Works
          a. Building B : 98%
          b. Lower Ground Floor & Pool  : 43%
      2. Architectural Works
          a. Building B  : 40%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building B : 45%

NaN/5

Bali Water World C
Bali, Indonesia

1. Structural Works
         a. Building C : 98%
         b. Lower Ground Floor & Pool : 43%
      2. Architectural Works
          a. Building C : 41%
      3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building C : 31%

NaN/6

Bali Water World D
Bali, Indonesia

1. Structural Works
         a. Building D : 100%
         b. Pool : 98%
     2. Architectural Works
          a. Building D : 94%
     3. Mechanical, Electrical and Plumbing works (MEP)
          a. Building D : 75% 

NaN/5

Bali Water World E
Bali, Indonesia

   1. Structural Works
         a. Building E : 100%
         b. Pool : 98%
     2. Architectural Works 
         a. Building E : 76%
     3. Mechanical, Electrical and Plumbing works (MEP)
         a. Building E : 72%

NaN/5

Chumphon Building 3
Chumphon, Thailand

Completed: 86 %>
  • Working on roof structure (100%)
  • Waiting for electric work
  • Waiting for install doors and windows
  • Tiling work in the pool
  • Cleaning around the building
  • Put the waste water pipe behind the building
NaN/10

Samui Resort building A
Koh Samui, Thailand

COMPLETED
  • Install the power cord in to the Main Distribution Board.
  • Install aisles lamp 3rd floor.
  • Install doors flame and door 4th floor.
  • Painted door jamb 4th floor was completed
  • Install guardrail main stair 2nd and 3rd floor.
  • Install guardrail fire exit stair 2nd and 3rd floor
  • Install  MDB Boxes.
  • Install air condition 4th floor 80%
  • Setting guard rail main stair 1st-4th floor.
  • Setting telephone box control 1st – 4th floor.
  • Tile the front elevator 1st-4th floor.
  • Painted inside 1st-2nd floor.
  • Fire fighting system test.
  • Prepare for gardening
  • Install sanitary ware on 3-4 floors.
  • Keep external color work.
NaN/10

Samui Resort building B
Koh Samui, Thailand

COMPLETED
  • Install the power cord in to the Main Distribution Board.
  • Install electrical cabinet for 4th floor.
  • Setting up guard rail 4th floor.
  • Install support water meter.
  • Install glass and aluminum frame 1st and 2nd floor.
  • Setting main water for tub 1st – 4th floor.
  • Tile laying tub 1st – 4th floor.
  • Install water pipes, bathtub water systems.
  • Setting telephone box control 1st – 4th floor.
  • Install granite on the sink counter 1st – 3rd floor.
  • Install aluminum door 1st -2nd floor 95%
  • Installing electrical plugs and switches 3rd floor 70%
  • Install washbasin 3rd floor.
  • Leveling the room floor, 4th floor.
  • Floor tile + balcony 4th floor.
  • Leveling the floor on the 4th floor.
  • Laying floor tiles for walkways on the 4th floor. 
NaN/10

Samui Resort building C
Koh Samui, Thailand

COMPLETED
  • Install the ceiling structure 4th floor.
  • Install up guard rail 4th floor.
  • Tile laying fire exit stair 3rd and 4th floor.
  • Install granite on the wash basin 4th floor.
  • Check the completion of the cement under main stair 1st – 4th floor
  • Painting ceiling 4th floor.
  • Install guardrail fire exit stair 2nd and 3rd floor
  • Setting guard rail fire exit stair 2nd-3rd floor.
  • Install the lamp 4th floor.
  • Setting up the electric system into the elevator.
  • Painted inside 1st-2nd  floor 95%
  • Collect paint work around the floor 1-3.
  • Keep external color work.
NaN/8

Samui Resort building D
Koh Samui, Thailand

COMPLETED
  • Install SHERA wall.
  • Install rainwater pipes.
  • Plastering elevator wall.
  • Install electrical cabinets for 3rd and 4th floor.
  • Install air conditioned 4th floor (80%).
  • Tile grout elevator wall 1st – 4th floor.
  • Setting up ceiling under main stair 1st- 3rd  floor.
  • Setting ceiling 4th floor.
  • Install water pump for the building.
  • Painting skim coat 4th floor.
  • Masonry in front of the project to prepare the project signboard.
  • Plaster wall water pump room.
  • Firefighting system test.
  • Testing air conditioning systems.
  • Install the railing on the 4th floor (90%).
  • Install granite counters on floors 2-4 (95%)
  • Paint the 4th floor ceiling (40%) 
NaN/7

Samui Water World building A
Koh Samui, Thailand

  • Install the plumbing system 1st floor.
  • Setting main pipe system 1st   floor.
  • Tied steel frame  2nd floor.
  • Steel pole tied 2nd floor.
  • Setting up floor frame 2nd floor.
  • Pouring concrete 2nd floor.
  • Steel frame elevator wall 2nd floor.
  • Steel frame main stair 1st and 2nd floor.
  • Installation of a water supply pipe system 2nd floor.
  • Steel tie and assemble with elevator wall, 2nd floor
  • Steel tie and assemble on the 2nd floor column
  • Pull the floor posts on the 2nd floor
  • Remove the floor plan, floor 2
NaN/6

Samui Water World building B
Koh Samui, Thailand

  • Setting main pipe system 1st   floor.
  • Install the plumbing system 1st floor.
  • Pouring concrete beam.
  • Setting ground water system.
  • Pouring concrete elevator wall 2nd floor.
  • Setting pole frame 2nd floor.
  • Steel floor frame 2nd floor.
  • Tie steel frame 2nd floor.
  • Tie steel frame elevator wall 2nd floor.
  • Installation of a water supply pipe system
  • Setting electric pipe 1st floor.
  • Setting up scaffolding to receive floor 3
  • Build a wall with lintels on the 1st floor 
NaN/6

Samui Water World building C
Koh Samui, Thailand

  • Tied steel frame 2nd floor.
  • Tied steel frame elevator wall 2nd floor.
  • Pouring concrete pole 2nd floor.
  • Steel frame elevator wall 2nd floor.
  • Steel frame main stair 1st-2nd floor.
  • Installation of a water supply pipe system
  • Setting scaffold for 3rd floor.
  • Steel floor frame 3rd floor.
  • Setting electric pipe 1st floor.
  • Constructed 3rd floor
  • Place the floor post on the 3rd floor
  • Piping and plumbing system level 1
  • Assembled the bathroom 1st floor.
  • Wall on the 1st floor.
NaN/6

Samui Water World building D
Koh Samui, Thailand

  • Tied steel beam pool bar.
  • Setting main water pipe system 1st floor.
  • Tied steel frame pool bar wall.
  • Install the plumbing system 1st floor.
  • Tile steel pole frame 2nd floor.
  • Setting up floor frame 2nd floor.
  • Tied steel frame  2nd floor.
  • Tie steel frame main stair 1st-2nd floor.
  • Installation of a water supply pipe system
  • Tie steel frame main stair 1st-2nd floor
  • Pouring concrete on floors 1-2
  • Pouring concrete on the 2nd floor
  • Reproduction and curing of concrete posts on the 2nd floor
  • Setting up scaffolding to receive floor 3 
NaN/6

Boutique
Pattaya, Thailand

Completed: 70 %>
  • Exterior plastering work 98% completed.
  • Rooftop work 98% completed.
  • Tilling bathroom wall on 3rd-7th floor 95% completed.
  • Tilling on 1st floor 60% completed.
  • Tilling  on 2nd-6th floor 80% completed.
  • Tilling on 7th floor 70% completed.
  • Ceiling work on 1st-4th floor 75% completed.
  • Ceiling work on 5th-6th floor 70% completed.
  • Ceiling work on 7th floor 15% completed.
  • Electric system work on 2nd-4th floor 92% completed.
  • Electric system work on 5th-6th floor 60% completed.
  • Water drains work on 2nd-7th floor 85% completed.
NaN/12

Club 4
Pattaya, Thailand

Completed: 97 %>
  • Exterior painting work 100% completed.
  • Room painting on 2nd-7th 99% completed.
  • The walk way painting on 2nd-7th floor 99% completed.
  • Ceiling work on 1st floor 95% completed.
  • Ceiling work on 2nd-7th floor 100% completed.
  • Balcony guard rail painting on 2nd-7th floor 99% completed.
  • Swimming pool electrical system work 100% completed.
  • Water drains work on 2nd-7th floor 100% completed.
  • Electric work (Wait for testing).
NaN/6

Club 5
Pattaya, Thailand

Completed: 7 %>
  • 2nd floor work 100% completed.
  • Pole work.
NaN/6

Marcus Hotel
Pattaya, Thailand

Clearing of land for Marcus Hotel completed

NaN/3

Palace Hotel
Pattaya, Thailand

Completed: 15 %>
  • Swimming pool structure work on 1st floor 30% completed.
  • Filling the soil around buildings 40% completed.
  • 1st floor structure 20% completed.
  • Parking Structure 20% completed.
NaN/6

The Castle Hotel
Pattaya, Thailand

  • Electric system on 2nd floor.
  • Painting ceiling work on 2nd floor.
  • Wall work on 1st floor.
  • Roof top work.
  • Installing Air condition on 2nd floor.
NaN/5

The Castle II
Pattaya, Thailand

Completed: 99 %>
  • Bricklaying work on the underground floor 99% completed.
  • Plastering underground wall 99% completed.
  • Plastering work on 1st-8th floor 99% completed.
  • Wash basin counter work 88% completed.
  • Plastering wall work on rooftop floor 100% completed.
  • Tilling work on 1st-8th floor 99% completed.
  • Tilling work on rooftop floor 100% completed.
  • Install skirting boards 98% completed.
  • Install wood door 45% completed.
  • Outdoor painting work 51% completed.
  • Interior wall painting work 90% completed.
  • Ceiling work 96% completed.
  • Installing UPCV window on 2nd-8th floor 90% completed.
  • Shower screen work on 2nd-8th floor 30% completed.
  • Elevator work 80% completed.
  • Electric system work 1st-8th floor 99% completed.
  • Water system work 97% completed.
NaN/10

Bangtao Water World B
Phuket, Thailand

  • Piling work of building D
  • Digging foundation work for building B.
  • Building the retaining wall block.
NaN/3